Why start CoD component estimates with a baseline value of 1?

Prepare for the SAFe Scaled Agile For Enterprise Certification. Explore our flashcards and multiple choice questions. Get ready for your exam with instant explanations and insightful hints.

Multiple Choice

Why start CoD component estimates with a baseline value of 1?

Explanation:
In WSJF, the Cost of Delay components are tied to a common reference unit so you can compare items quickly and fairly. Starting each CoD component at a baseline of 1 anchors the scale, making the numbers purely relative rather than tied to absolute dollars or hours. When you rate components like business value, time criticality, and risk reduction, a score of 3 means three times the baseline value, and you get a simple sum for the CoD (for example, 3 + 2 + 1 = 6). This keeps the Cost of Delay a clear, interpretable relative measure that, when divided by the job size, yields a consistent, comparable WSJF value across backlog items. It also prevents zeros and keeps the math straightforward, which supports consistent decision-making.

In WSJF, the Cost of Delay components are tied to a common reference unit so you can compare items quickly and fairly. Starting each CoD component at a baseline of 1 anchors the scale, making the numbers purely relative rather than tied to absolute dollars or hours. When you rate components like business value, time criticality, and risk reduction, a score of 3 means three times the baseline value, and you get a simple sum for the CoD (for example, 3 + 2 + 1 = 6). This keeps the Cost of Delay a clear, interpretable relative measure that, when divided by the job size, yields a consistent, comparable WSJF value across backlog items. It also prevents zeros and keeps the math straightforward, which supports consistent decision-making.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy