What is one output of I&A program performance reporting?

Prepare for the SAFe Scaled Agile For Enterprise Certification. Explore our flashcards and multiple choice questions. Get ready for your exam with instant explanations and insightful hints.

Multiple Choice

What is one output of I&A program performance reporting?

Explanation:
In SAFe, Inspect & Adapt at the program level produces metrics that show how reliably an Agile Release Train delivers its planned releases. One key output is the Release predictability report, which summarizes how well release plans align with actual delivery over time, highlighting variance between planned and actual release dates and trends to improve forecasting. Visual wall charts are useful for transparency, but they’re generic program visuals rather than a formal I&A performance report. A burn-down chart tracks team-level progress within a sprint, not program-level release performance. The sprint backlog is a team artifact, not a program performance output.

In SAFe, Inspect & Adapt at the program level produces metrics that show how reliably an Agile Release Train delivers its planned releases. One key output is the Release predictability report, which summarizes how well release plans align with actual delivery over time, highlighting variance between planned and actual release dates and trends to improve forecasting.

Visual wall charts are useful for transparency, but they’re generic program visuals rather than a formal I&A performance report. A burn-down chart tracks team-level progress within a sprint, not program-level release performance. The sprint backlog is a team artifact, not a program performance output.