In SAFe, establishing velocity is used to determine what during sprint planning?

Prepare for the SAFe Scaled Agile For Enterprise Certification. Explore our flashcards and multiple choice questions. Get ready for your exam with instant explanations and insightful hints.

Multiple Choice

In SAFe, establishing velocity is used to determine what during sprint planning?

Explanation:
Velocity is the amount of work a team can complete in a sprint, usually measured in story points. In sprint planning, this helps determine how many backlog items the team can commit to delivering in the upcoming iteration, setting a realistic, achievable scope based on the team’s historical throughput. It’s a measure of capacity, not the release cycle length, the number of stakeholders, or the types of backlog items to include. Release cadence and PI planning guide overall timing, stakeholder governance is separate, and item type decisions come from prioritization and architecture needs, not velocity.

Velocity is the amount of work a team can complete in a sprint, usually measured in story points. In sprint planning, this helps determine how many backlog items the team can commit to delivering in the upcoming iteration, setting a realistic, achievable scope based on the team’s historical throughput. It’s a measure of capacity, not the release cycle length, the number of stakeholders, or the types of backlog items to include. Release cadence and PI planning guide overall timing, stakeholder governance is separate, and item type decisions come from prioritization and architecture needs, not velocity.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy