In Agile drivers, which statement best describes the relationship between dates and scope?

Prepare for the SAFe Scaled Agile For Enterprise Certification. Explore our flashcards and multiple choice questions. Get ready for your exam with instant explanations and insightful hints.

Multiple Choice

In Agile drivers, which statement best describes the relationship between dates and scope?

Explanation:
Agile treats time as a hard constraint and lets scope adapt to fit that time. In practice, you set a fixed date (or release milestone) and prioritize what will be delivered within that window, adjusting or deferring less essential work to meet the deadline. This is why the best description is that dates are fixed and scope can float. If you fix the scope and move the date, you’re chasing a moving target, which is less aligned with Agile practice. If you fix both date and scope, you lose the ability to adapt to new priorities or learnings. The idea that the vision cannot be used to estimate features misses the point of how time and scope interact in planning, which is to fit the most valuable work into the fixed timebox.

Agile treats time as a hard constraint and lets scope adapt to fit that time. In practice, you set a fixed date (or release milestone) and prioritize what will be delivered within that window, adjusting or deferring less essential work to meet the deadline. This is why the best description is that dates are fixed and scope can float.

If you fix the scope and move the date, you’re chasing a moving target, which is less aligned with Agile practice. If you fix both date and scope, you lose the ability to adapt to new priorities or learnings. The idea that the vision cannot be used to estimate features misses the point of how time and scope interact in planning, which is to fit the most valuable work into the fixed timebox.